How do I plan a fallback when a critical project input may not arrive?
Quick answer
List the decisions and tasks that depend on the missing input, then separate work that can continue from work that must wait. Agree on a trigger, such as a date or a confirmed delay, for reviewing a fallback. Choose a limited option that preserves useful progress, label any assumptions, and identify who must approve it before it becomes final. Record how you will switch back when the expected input arrives.
The question, the details, the next step.
A practical checklist
Name the missing input, its owner, and the expected date or event.
List the decisions and tasks that depend on it; separate blocked work from work that can continue.
Set an observable trigger and a review point, and name the decision owner.
Describe a limited fallback using confirmed information; mark assumptions and unresolved sections.
State what the fallback may be used for, what remains paused, and who must approve it.
Record how the team will update the work when the expected input arrives or changes.
A few more useful answers
What if no alternative can preserve meaningful progress?
Record what is blocked, what decision or input would unblock it, and when the situation will be reviewed. A fallback can be to pause the dependent work and continue only independent tasks; it does not have to invent a substitute.
Should a fallback use assumptions?
Only if the relevant decision owner agrees that assumption-based work is appropriate. Label each assumption, limit what the draft can be used for, and keep approval-dependent decisions open.
What if the expected input arrives after the fallback starts?
Compare the new input with the pending sections and assumptions, update the affected work, and obtain any required review. Tell the team which version or sections have changed.