How do I record a project requirement change without losing the original agreement?
Quick answer
Keep the original requirement intact and add a separate, dated entry for each proposed change. Record who requested it, what would change, who decided, when the decision was made, and which work is affected. Do not mark the earlier requirement as superseded until the change is approved. Link the relevant drafts or decisions, and clearly identify the current version so readers can distinguish history from instructions to follow now.
The question, the details, the next step.
A practical checklist
Keep the original requirement and identify its version or location.
Give each proposed change a unique ID and date raised.
Record the request, reason, decision, decision-maker, and decision date.
Name affected work, its owner, and the next action.
Label the status clearly and update the active requirement only after approval.
Link later changes to earlier entries instead of rewriting history.
A few more useful answers
Should I delete a requirement after it is replaced?
Keep the original wording in the history and mark it superseded, with a link to the approved replacement. That preserves the earlier agreement without presenting it as current.
What if the change was agreed verbally?
Record the date and the decision as you understand it, then ask the relevant decision-maker to verify the written entry. Mark it pending confirmation until they do.
How much detail should the reason include?
Use a brief, plain-language explanation of the stated reason for the request. Keep it separate from the decision, and avoid adding an explanation that nobody agreed to.